Rafters are on!

This week we have made much better progress, now that some reasonable weather is here.
By the end of Monday we had completed weaving the walls on three of our buildings

The completed walls on two of the buildings.

The completed walls on two of the buildings.

The next task was to insert the central four pairs of rafters into the walls, these are inverted so that the tip of the rod goes into the wall weave. This allows the rafters to be bent over, creating a curve.

The rafters are inserted into the woven hazel wall.

The rafters are inserted into the woven hazel wall.

After tying the rafters to the ridge pole we fitted more rafters to the ends of the building, bending them over to meet a cross brace that was tied to the central rafters.

The rafters are temporarily tied.

The rafters are temporarily tied.

These rafters are temporarily fixed to the cross brace supporting the roof structure over the weekend. We will return on Monday to adjust and fix them permanently.

One set of end rafters in.

One set of end rafters in.

The progress at the end of week 3.

The progress at the end of week 3.

Advertisements

One thought on “Rafters are on!

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s